Building Department’s General Permit Application Process:

The process starts when the Building Department receives an Application (General Permit Application to be used for every project).

1. Application must be complete – all pertinent information must be submitted (see Permit package (project-specific) for work being done).
2. A pre-site inspection is scheduled with the Applicant/Contractor.
3. After the site inspection, a plan review is done by the Building Inspector.
4. Once the Application has been approved, a Permit will be issued.
5. We will call for Permit pick-up when ready.
6. Permit cards should be posted, and work may begin.
7. The Applicant/Contractor should call in for all inspections. This will be discussed at the pre-site inspection.
8. A Final Certificate will be issued once the final inspection has been completed and passed.

Please note:  A Certificate of Occupancy fee is required, if applicable.


Click here to visit the Building Permit Applications & Forms page for all Building Permit and Engineering Permit Applications and the Current Fee Schedules.


The Building Department is located on the Lower Level of the Town Hall. The entrance is at the rear of the building.

The Building Inspectors, Fire Inspector, Stormwater Management Officer, Zoning Officer, and Floodplain Administrator can be found in the Building Department offices.